Saving three tons steel melting furnace proper use

Update Time: 2019-01-25 09:09:51

Saving three tons steel melting furnace proper use

(A) connecting three tons steel melting furnace main terminal and a secondary line

1 , the main wiring:

The power supply line is made of copper core cable, and the cross-section of each phase is not less than the listed value.

 

rated power

KW )

Three-phase incoming cross-sectional area ( mm2 )

100

100

The power supply and load are connected by ( 4 mm2 ) 25 sets of two-color stranded wires, and the contact at the joint should ensure good and reliable.

2. Note: The main cabinet and the capacitor load cabinet must be reliably connected to the ground.

(B) prior to start checking the steel melting furnace 3 t:

Check that all components are in good condition;

Check that all fasteners are in good condition;

Check if all the wires are disconnected and whether the solder joints are desoldered;

Check if the connection in the installation is correct;

Check the main circuit with a multimeter, and control the insulation of the casing and the insulation between the phases;

Check if the control plugin is placed correctly.

Open the inlet valve and adjust the water pressure to 0.1 ~ 0.2Mpa to check for leaks in each waterway.

(C) 3 t steel melting furnace transmission check:

1. Strictly check the phase sequence. A correspondingly advances the phase B by 120 ° degrees, and C corresponds to the phase B of 120 ° degrees.

2 , control power switch AQ1 , the power indicator of each control board should be on.

3. Check the rectification and inverter trigger pulses with an oscilloscope.

4. Trigger the protection thyristor and the corresponding protection indicator lights.

5. Set the power potentiometer to 0 position, dial out the control board, and check that the relay action should be normal.

D) 3 t steel melting furnace Procedure

1. The operation instructions are shown in Table 3.

 

Serial number

Name

symbol

Use

1

AC voltmeter

M1

Indicating AC incoming line voltage

2

DC ammeter

M3

Indicates the main circuit DC current

3

DC voltmeter

M2

Indicates the main circuit DC voltage

4

Output voltmeter

M4

Indicates the output peak voltage

5

Control power indicator

LM1

Lights up to indicate that the control loop is powered

6

Main power indicator

LM2

Lights up to indicate that the main circuit is powered

7

Inverter work indicator

LM3

Lights up to indicate that the power supply is working

8

Over current indicator

LM4

Lights up to indicate that the power supply has an overload or short circuit fault.

9

Overvoltage indicator

LM5

Lights up to indicate that the power supply has an overvoltage fault.

10

Low water pressure indicator

LM7

The water pressure is low until the setting value is on, the power supply cannot be started or automatically stopped.

11

Control button

AQ1

Control system power supply after pressing

12

Control sub button

AT1

Control system is powered off after pressing

13

Main power button

AQ2

After pressing, the main circuit rectifier bridge and the power supply are closed.

14

Main power sub button

AT2

After pressing, the main circuit rectifier bridge and power supply are disconnected.

15

Inverter work button

AQ3

Power is ready to start after pressing

16

Inverter stop button

AT3

After the inverter is pressed, the inverter bridge stops working and the protection system is reset.

17

Power adjustment potentiometer

W2

Adjust to zero position before starting. Turn the knob clockwise after starting, the power output power increases

18

Temperature alarm indicator

LM6

If the water temperature exceeds the setting value, the power will not start or stop automatically.