Luoyang Songdao Induction Heating Technology

POSITION:HOME > NEWS >

Technical requirements for the water cable of the induction melting furnace:

Update Time: 2022-08-01 10:28:45

Technical requirements for the water cable of the induction melting furnace:

1. The cross-sectional area of the copper stranded wire, the unit is mm2 

2. The current carrying capacity of the copper stranded wire, the unit is A 

3. The rated voltage of the water cable, the unit is V 

4. Cooling water flow rate, the unit is m3/h 

5. The minimum bending radius of the water cable of the induction melting furnace, the unit is mm 

6. The geometric mean radius GMR of the water cable of the induction melting furnace, the unit is mm 

7. The working pressure of the water cable of the induction melting furnace, the unit is Mpa  length, the unit is m  weight, the unit is kg 

8. The breakdown voltage of the water cable outer sheath hose of the induction melting furnace is V2300V.  

9. The water cable outer sheath hose of the induction melting furnace can withstand working water pressure P0.6Mpa.  

10. There is no leakage of cooling water between the water cable outer jacket hose and the electrode interface of the induction melting furnace.  

11. The water cable copper strands and electrodes of the induction melting furnace are cold-extruded and fastened on special equipment.